1. Pull out on locking tab (2), then install new circuit breaker (1) onto mounting rail (3).
2. Connect wires to circuit breaker (1) as tagged.
3. Position lever (4) to ON.
4. Turn handle (5) CW, then close door (6).
5. Secure door (6) to main control enclosure (7) by tightening eleven latches (8).
6. Verify correct operation as follows:
a. For circuit breaker CB7:
1. Position MAIN POWER switch (WP 0009 00, Figure 1, 1) to ON.
2. Verify MAIN POWER lamp (2) is on.
3. Position CONTROL POWER switch (3) to ON.
4. Verify CONTROL POWER lamp (4) is on.
b. For circuit breaker CB8 use maintenance menu to test air system (WP 0010 00). Also test external lighting.