TM 10-3510-226-23
0068 00
ADJUST
Adjust the Thermostat
WARNING
Ensure that all electrical power to the boiler is shut off and disconnected before
proceeding. The circuit breaker box or individual circuit breaker should be locked and
tagged out by personnel following this procedure. Remember that the CBL is a wet
environment. Serious injury or death to personnel can result from electrocution if proper
safety precautions are not observed.
WARNING
Allow the boiler and any associated hot water pipe, tubing or fixtures to cool at least 30
minutes before attempting any repairs. Failure to observe safety precautions may result
in serious injury or death to personnel.
NOTE
The thermostat has been designed for adjustment without removal of the cover, but
removal of the cover is recommended to ensure adequate visual verification of the
setting.
1. Switch the boiler off at circuit breaker No. 22, and allow the boiler to cool for at least 30 minutes
before proceeding.
2. Loosen the screw retaining the thermostat cover (Figure 9, Item 5), and remove the cover.
3. Ensure the dial (Figure 9, Item 7) has been set for approximately 205 oF.
4. Install the thermostat cover (Figure 9, Item 5), and retain with screw.
5. Switch the boiler on at circuit breaker No. 22, and operate the boiler for at least 30 minutes IAW
procedures given in TM 10-3510-226-10.
6. Monitor for normal operation.