Open the personnel entry doors marked OPEN FIRST, then open the opposite doors marked REAR DOOR.
Loosen and remove tie-down straps secured to the provisions on the floor. Place straps into footlocker
after setup is complete.
WARNING
At least four persons are required to unpack the CSSL. To avoid injuries,
observe the lift requirements shown in the table below.
Unpack the CSSL and identify and inventory items being removed using the table below and the packing
plan on the following page. Position the unpacked items as shown in the illustration on page 0005 00-5.
Check condition of components during unpacking and report any discrepancy to your supervisor.
Table 0005 00-1. CSSL Contents
Nomenclature
Quantity
Condition
Lift Requirements
100AMP Cable, 50ft
2
Clean, coiled, caps installed
2 Persons each Cable
TEMPER Frame Section Cover
1
Clean and folded
4 Persons
TEMPER, 8ft Window Section
1
Clean and folded
4 Persons
TEMPER Modified End Section
1
Clean and folded
4 Persons
TEMPER End Section
1
Clean and folded
4 Persons
Fresh Water Supply Hose 1 ½
1
Drained and coiled
2 Persons
Wastewater Drain Hose 2
1
Drained and coiled
2 Persons
Ground Rod
1
Clean, with wire attached
1 Person
Ventilation Fan
1
Cord Plug taped to body
2 Persons
Wastewater Tank 3,000 Gallon
1
Drained clean and folded
4 Persons
Freshwater Tank, 3,000 Gallon
1
Drained clean and folded
4 Persons
Table, Folding
4
Folded and tied
1 Person each table
Portable Fluorescent Light Assy
1
In Case
1 Person
Tie Down Straps
4
Secured to floor provisions
1 Person
Footlocker, containing:
1
1 Person
Garden Hose
1
Drained, coiled, ends connected
Technical Manual
1
In plastic bag
120 VAC Power Cord
1
Clean and coiled
Adjustable Wrench
1
Clean
Flash Light
1
Clean
Washer/Dryer Repair Parts
Original Pack
Release