TM 10-3510-226-23
0083 00
REPLACE-CONTINUED
11. Install replacement dryer (Figure 2, Item 4) into CBL operating area.
12. Remove dryer lint compartment panel (Figure 2, Item 5).
13. Move replacement dryer (Figure 2, Item 4) into position and align mounting holes.
14. Install mounting bolts (Figure 2, Item 6) and tighten.
15. Remove junction box cover (Figure 1, Item 1) on replacement dryer.
16. Knock out conduit access if necessary, install conduit (Figure 1, Item 2), and retain with conduit
locknut.
17. Connect wiring to replacement dryer (Figure 2, Item 4) as tagged.
18. Install junction box cover (Figure 1, Item 1) and retain with screws.
19. Install duct (Figure 1, Item 3) onto replacement dryer exhaust and secure with hose clamp.
20. Raise and refit TEMPER IAW procedures given in TM 10-3510-226-10.
21. Connect power and monitor for normal operation.
3
2
1
Figure 1. Replace the Dryer.
0083 00-2