TM 10-4510-209-13&P
0013 00
Table 1. Main Power Troubleshooting Procedures.
MALFUNCTION
TEST OR INSPECTION
CORRECTIVE ACTION
1. LOSS OF POWER
Reset breaker by setting the main
Step 1. Check that main breaker
breaker (#1/3/5) to the OFF
(2) #1/3/5 is set to the ON
position and then back to the ON
position and has not tripped.
position.
Reset breaker by setting the
Step 2. Check that circuit
breaker to the OFF position and
breakers on DISE box (3) are set
then back to the ON position.
to the ON position and have not
tripped. (For CL only)
Step 3. Ensure the 60A power
Notify Unit Maintenance.
cable is connected to the power
panel.
2
2
Containerized Latrine
Containerized Latrine System
0013 00-2