Procedure 3: No Water Pressure
INITIAL SETUP:
Equipment Condition
Materials/Parts
CSSL set-up, but not in operation
None
Maintenance Level
nit
U
CONNECT THE 20 FT, 2" FRESHWATER HOSE TO
THE INTENDED WATER SOURCE AND THE
FRESHWATER INLET PANEL AS DESCRIBED IN
WORK PACKAGE 0005 00. ENSURE WATER IS
AVAILABLE AT SOURCE.
CHECK IF COMMERCIAL WATER SOURCE IS
SUPPLYING WATER. ENSURE 3,000 GALLON
FRESHWATER TANK CONTAINS SUFFICIENT
WATER. CHECK HOSE CONNECTION TO
SOURCE.
ENSURE CIRCUIT BREAKER #3 IN RIGHT SIDE
POWER DISTRIBUTION PANEL IS SET TO ON.
LIFT AND HOLD LEVER ON PRESSURE SWITCH
UNTIL PRESSURE GAUGE READS 20LBS. (REFER
TO WORK PACKAGE 0005 00)
FRESHWATER PUMP REQUIRES PRIMING.
NOTIFY DIRECT SUPPORT MAINTENANCE.
NO
YES
NO
NO
NO
YES
YES
IS COMMERCIAL SOURCE TURNED ON? OR, IS
FRESHWATER TANK (IF USED) FULL AND 2 "
WATER HOSE PROPERLY CONNECTED TO IT?
IS FRESHWATER PUMP OPERATING ?
AFTER RUNNING PUMP FOR SEVERAL MINUTES, IS
PRESSURE ON THE PRESSURE GAGE
INCREASING?
IS 20 FT, 2 " FRESHWATER HOSE PROPERLY
CONNECTED TO WATER SOURCE AND CSSL
FRESHWATER INPUT PANEL ON UTILITY WALL?
YES
OPERATE CSSL
END OF WORK PACKAGE