PREPARE POWER DISTRIBUTION SYSTEM FOR SHIPMENT.
WARNING
Power source must be shut down/secured before disassembling any cables to
prevent electrical shock.
NOTE
This procedure can only be performed by qualified civilian or military personnel in
MOS 51R, 52C, 52D, or 52G.
1. Set all individual and then the main circuit breakers in both power distribution panels (1) to OFF. Turn power
source OFF. Disconnect 100 AMP Supply Cables (2) from the power entry panel (3) and from the power source.
2. Disconnect power cables, if being used, from the 110 VAC GFCI Utility (4), 30 AMP twist-lock (5) and the 60 AMP
Class L connector (6) on the power entry panel (3).
3. Install dust covers on all power entry panel connectors and 100 AMP Supply Cables (2). Coil the cables.
4. Disconnect the ground wire (7) from the ground terminal on the power entry panel (3). Recover the ground rod (8),
disassemble it and clean it.