This task covers: a. Inspection b. Disassembly/ Removal c. Assembly/Installation
INITIAL SETUP
Tools:
Equipment Conditions:
Shower facility not in use.
Item 1)
Materials/Parts:
a. Inspection. Check for damage, deterioration, or missing parts. Based on the inspection, determine to what extent
the hose assembly must be disassembled to be repaired or replaced.
NOTE
Repair is limited to replacement of defective, missing, or damaged
components. Disassemble only to the extent necessary to repair the item.
b. Disassembly/Removal.
(1) Loosen two clamps (1) then pull hose (2) end off coupling (3) and remove clamps.
(2) Loosen two clamps (4) then pull hose (2) end off coupling (5) and remove clamps.
(3) Remove couplings (3 and 5) from pump assembly.
c. Assembly/Installation.
(1) Be sure any defective, missing, or damaged components have been replaced.
NOTE
Supply pump cold line hose assembly couplings are issued as a set.
(2) Apply sealing compound to threaded end of coupling (3) and threaded end of connector (5) mating connector.
Install couplings into pump assembly.
(3) Slide two clamps (4) over hose (2) end and install hose onto coupling (5). Be sure clamps are around coupling
and tighten clamps.
(4) Slide two clamps (1) over hose (2) end and install hose onto coupling (3). Be sure clamps are around coupling
and tighten clamps.
(5)
4-23