6. Install remaining purlin diagonal braces (9) repeating steps 3 through 5 above. Stagger the placement
of the diagonal braces as shown below.
9
9
7. Install purlin (1) at each eave (3) repeating steps above. Begin at step " 2. Start at the ridge..."
Then, install purlin (1) at each base (4) repeating steps above. Begin at step " 2. Start at the ridge..."
8. Add eight foot TEMPER frame sections as required by installing additional purlin assemblies,
repeating steps 1 through 7. When completed, the frame section is now in a kneeling position.
1
4
3
1