TM 10-3510-209-24
2-24. AIR COMPRESSOR (CONT)
INSTALLATION
1.
Position air compressor (2) on platform (19).
2.
Install four bolts (18), lockwashers (17), and nuts
(16).
3.
Install conduit (14) and conduit nut (13) on
pressure switch (15).
4.
Connect four input wires (12) coming from
conduit (14). Remove tags. Refer to FIGURE 2-7.
5.
Connect compressor-to-airtank air line (11) to air
compressor (2).
6.
Turn on power to compressor.
7.
Check for proper rotation.
8.
Perform ADJUSTMENT procedures.
9.
Install pressure switch cover (6) and tighten
captive acorn nut (5).
NOTE
FOLLOW-ON MAINTENANCE:
Install pre-extraction bin (para 2-27).
2-96 Change 1