If the pump is to be used after installation, priming will be necessary. To prime the freshwater pump,
proceed as follows:
Close the gate valve (1 on the pump drain line and the gate valves (2) and (3) on the main supply line.
Remove the priming plug (4 on top of the pump. Fill the pump with freshwater and replace the priming
plug (4).
Ensure ball valve (5) on freshwater line is in the open position (aligned with pipe) Place the pump cover
(6) over the pump and align with the mounting holes (7). Install screws (8). Install the pressure switch (9)
as described in work package 0036. Plug the freshwater pump power cord (10) into the receptacle
marked on the curbside raceway (11). Replace cable ties as necessary. Set circuit breaker 28 on power
distribution panel #1 to ON. Disconnect garden hose from freshwater line drain fitting. To place the pump
in operation, follow procedures in work package 0005 00-16.