TM 10-3510-223-13&P 0005 00
0005 00-30
Moving the TEMPER Section into Position
WARNING
The assembled TEMPER is heavy. At least four persons are required to
move the TEMPER into position. To avoid injuries, ensure personnel are
available before attempting to lift the tent. Personnel in the 5th percentile
size group may require a step aide during this procedure.
Using four soldiers, one at each side arch assembly (1), pick up and move the TEMPER section against
the CSSL, centering the ridge on the TEMPER section with the center of the closed personnel doors.
Have two soldiers gain access to top of CSSL using the hinged steps. Pull the boot (2) over the container
end and lay loosely on the container roof.
Locate two bootwall lines (3) attached to the bootwall fabric and pull them towards the opposite corners of
the CSSL as shown. DONOT FASTEN THESE LINES AT THIS TIME.
1
2
3