Table 1. Preventive Maintenance Checks and Services for Containerized Shower
and Shower, Enclosed Unit, System - continued
Item To Be
Equipment
Item No.
Interval
Checked Or
Procedure
Not Ready/
Serviced
Available If:
Frayed or other-wise
4
Before
Power Cables,
damaged power supply
Service Panel,
cable. Improper
and Grounding
connections on power
Rod/Connector
service panel.
WARNING
Container not properly
grounded.
Lethal voltage is present if the
Containerized Shower or Shower,
Enclosed Unit, System is connected
to a power source. Ensure power
source is OFF during PMCS.
Inspect the power supply cables (1)
for visible damage. Check for frayed
insulation, loose connections (2), or
cables laying in water. Check the
connections to the power service
panel (3). Inspect grounding rod (if
used) (4) for secure emplacement
and connection to grounding terminal
(5).