TM 10--3510--221--10
0010 00--3
LAUNDRY ADVANCED SYSTEM OPERATION UNDER USUAL CONDITIONS
DAILY OPERATING PROCEDURES -- Continued
0010 00
DAILY OPERATING PROCEDURES -- Continued
A. System Start--up -- Continued
NOTE
For continuous laundry operations always start with full water tanks for both systems.
If a laundry cycle is started without enough water in the tanks the laundry cycle will
be interrupted.
12. Press appropriate MENU SELECTION switch as follows:
a. Select FILL TANKS to fill all water tanks to proper level. Proceed to step 13.
b. Select OVERRIDE FILLING to bypass water filling. Proceed to step 15.
NOTE
It will take approximately 15 minutes for tanks to fill when completely drained.
13. Monitor display (6), it should read:
FILLING WATER TANKS
OVERRIDE FILLING
EXAMINE INPUTS
14. Wait for tanks to fill then proceed to step 15.
15. Monitor display (6), it should read:
SET WATER TEMPERATURE
HEAT WATER
MODIFY SETPOINT
OVERRIDE HEATING
SETPNT= XXX F TEMP = XXX F
EXAMINE INPUTS
NOTE
If the water heating operation is stopped while in progress, OVERRIDE FILLING
should be selected when system is restarted. Selecting the FILL TANKS option will
result in excess water being added to the rinse 2 tank.
16. Slide air inlet filter (1) out of heater (2).
WARNING
When priming fuel supply, reading at pressure gauge (7) must be at ZERO. If
pressure at this gauge increases when the PRIME PUMP switch in on, STOP the
priming operation and notify Unit manintenance. Attempting to start the heater with
excess fuel in the combustion chamber can cause an explosion and injury to
personnel.
17. Prime fuel supply to heater (2) as follows:
a. Lift and hold PRIME PUMP switch (3).
b. Observe reading on pressure gauge (4).
c. Release switch (3) when pressure gauge (4) remains steady at 135 psi or higher for a continuous 120
second period.
18. Slide air inlet filter (1) back into heater (2) with direction arrow (5) pointing towards heater inlet.