TM 10--3510--221--24
0152 00--3/4 blank
INLET A WATER CONTROL VALVE
REPLACEMENT -- Continued
0152 00
INSTALLATION
1. Apply anti--seizing tape to threads of elbows (4).
2. Thread two elbows (4) into new control valve (5).
3. Apply pipe thread sealant to threads of inlet A manifold (2) and adapter (18).
4. Thread adapter (18) into control valve (5).
5. Thread control valve (5) onto inlet A manifold (2) and orient as shown.
6. Install new gaskets (17) onto inlet A manifold (2).
7. Position inlet A manifold (2) under water tanks (9).
8. Attach inlet A manifold (2) to water tanks (9) as follows:
a. Mate each adapter (18) to fitting on water tanks (9) ensuring gasket (17) remains in place.
b. Install clamp (16).
c. Repeat steps a and b at other two connection points.
9. Connect tubes (3) to elbows (4) on three control valves (5) as tagged.
10. Attach tubes (3) to inlet A manifold with tiedown straps.
11. Mate support leg (8) to water tanks (9) then install, but do not tighten, two screws (6) and lock washers (7).
12. Install two screws (10), flat washers (11), and nuts (12) to secure support leg (8) to ISO frame (13).
13. Tighten two screws (6).
14. Connect hose (15) to inlet A manifold (2) tighten clamp (14).
15. Install cap (1) onto inlet A manifold (2).
16. Install inlet B manifold (WP 0151 00).
17. Perform a FILL TANKS, HEAT TANKS, and test laundry cycle operation (TM 10--3510--221--10). While water is
circulating visually check for water leaks.
END OF WORK PACKAGE