1.
Final Preparation.
(1)
Rotate tarpaulin support frames up on Laundry Unit and install bottom bolts, washers, and nuts. (Hardware
in toolbox).
(2)
Install tarpaulin per substeps below: See figure 2-28.
(a)
Position tarpaulin on top of Laundry Unit and unfold.
(b)
Pull the four sides down from the top.
(c)
Find first lace and grommet next to top of the corner.
(d)
Insert first and second laces through f irst and second grommets.
(e)
Insert second lace up through loop in first lace.
(f)
Pull second lace tight.
(g)
Insert third lace through grommet and through loop in second lace.
(h)
Pull third lace tight.
(i)
Continue lacing and insert next-to-last lace through loop in last lace.
(J)
Pull the next-to-last lace tight and tie off with half-hitch knot.
(k)
Close weather flap.
(I)
Continue on until all corners are laced and close weather flaps.
(m)
Hook fibrous rope on trailer (four corners).
2-85