TM 10-3510-223-13&P
0032 00
CONTAINERIZED SELF SERVICE LAUNDRY (CSSL) MODEL A
DIRECT SUPPORT MAINTENANCE PROCEDURES
0032 00-1
POWER DISTRIBUTION PANEL
THIS SECTION COVERS:
Test, Replace
INITIAL SETUP
CSSL shut down (Power connected)
Maintenance Level
Materials/Parts
Direct Support
Wiping Rags (WP 0072 00, Table 1, Item 1)
Tools and Special Tools
Tags, Marking, (WP 0072 00, Table 1, Item 10)
Tool Kit, Electronic Equipment (WP 0045, Table 2, Item 3) Tape, El. Insul. (WP 0072 00 Table 1, Item 15)
WARNING
This equipment operates at high voltage. Use extreme caution during
testing procedure. Touching a live wire can cause serious injury or death.
This procedure can be performed only by qualified civilian or military
personnel in MOS 51R, 52C, 52D, or 52G.
TEST
With 208 Volt 3 Phase 100AMP power connected to the power entry box plug(s)(1) and (2) and using a
multimeter set to read AC Voltage, determine the availability of power at both power distribution panels
main breakers (#11) (3). Test individual breakers as necessary to isolate a malfunction. Refer to CSSL
power schematic/wiring diagram, Figure 10, at end of manual.
BREAKER
MAIN
D
BREAKER
MAIN
D
2
1
3
4