Install
Place a new distribution box (1) (modified as specified in work package 0074 00, Figure 9) onto the wall
studs on the container wall and install four retainer hex nuts (2) onto the wall studs. If applicable, place
the phase indicator (3) into position on power distribution panel #1 and secure the angle bracket (4).
Place new breaker panel (5) into position on the bracket (6) and install six screws (7) holding the panel to
the bracket. Install individual breakers (8) onto breaker panel (5) and secure with flat head screw (9).
Re-connect tagged wires (10) onto breakers (8) ground bar (3 locations)(11) and breaker box (12). Place
new cover and door (13) onto bracket (6) and install four screws (14) to secure it. Close the circuit
breaker panel door.