Install
Temporarily place new alarm box (1) into position on wall mount studs (2) and conduit connector (3).
Mark center location of conduit connector (3) on bottom of alarm box (1) and drill proper hole size for
installation of connector into alarm box. Re-position alarm box (1) onto wall mount studs (2), feed wires
through hole, and install conduit connector (3). Install the four hex nuts and washers (4) that hold the
alarm box (1) to the wall mounts (2). Tighten conduit connector (3). Re-connect the electrical supply wires
onto the S1 terminal strip (Refer to panel layout illustration on page 0039 00-4 and the commercial
literature furnished with pump control panel). Set control to ON and pump to AUTO. Close alarm box
door. Set main breaker in power distribution panel #1 to ON. Push the ALARM TEST button to test the
operation of the new wastewater alarm. Push PUMP RUN to place new wastewater alarm in operation.