TM 10-3510-226-23
UNIT MAINTENANCE
CONTAINERIZED BATCH LAUNDRY
PRESSURE TRANSMITTER
REPLACE
INITIAL SETUP
Tools
Personnel Required
Quartermaster and Chemical Equipment
Table 2, Item 6)
Repairer 63J (1)
Materials/Parts
Equipment Condition
CBL shutdown
Item 51)
REPLACE
Replace Pressure Transmitter
NOTE
The CBL may be operated in minimum reuse or no reuse mode if necessary when
performing this maintenance task.
NOTE
The seven pressure transmitters are monitored by the PLC. A failure of this component
will be signaled by an alarm and a message at the PLC.
1. Drain system.
2. Disconnect power.
NOTE
Some transmitters may require removal of pipe clamps to provide clearance.
3. Loosen retaining screw and remove the electrical plug (Figure 1, Item 1) from the pressure
transmitter (Figure 1, Item 2).
4. Unscrew pressure transmitter (Figure 1, Item 2) from PVC bushing (Figure 1, Item 3).
5. Apply antisieze tape to threads of replacement transmitter (Figure 1, Item 2).
6. Screw replacement transmitter (Figure 1, Item 2) into PVC bushing (Figure 1, Item 3).
7. Connect electrical plug (Figure 1, Item 1) and retain with screw.
8. Connect power, and monitor for normal operation.