16. Place the three stair/ladders on their sides with their tops to the left.
17. Place the 6 water cans, on their sides, between the stair/ladder treads.
18. Place the ground rod slide hammer on top of the stair/ladders.
19. Strap the stair/ladders and slide hammer in place by bringing the two ratchet straps over them
and securing them to the rings on the floor. Tighten the straps securely.
20. Place the wing jacks, with their base plates to the left, on top of the stair/ladders. Slide the tops
of the jacks under the air conditioner and secure the jacks to the stair/ladders using two short
rubber straps.
21. If the corner jacks and screw jacks were used, separate the jack bodies from the
extension/base plates. Store the corner jacks bodies, their extension/base plates, and the
screw jack bodies in their storage brackets on the left door. Ensure that the jacks and base
plates are properly secured to the brackets.
22. Stow the screw jack extension/base plates on the floor to the left of the generator and strap
them down with a short rubber strap.
23. Ensure that the ends of the two air conditioner condensation drain lines are stowed inside the
mechanical room so they will not be damaged when the doors are closed.
24. Closing the left door first, close and latch the mechanical room doors.
25. Place all three fuel cans in a Food Service Section vehicle.
END OF WORK PACKAGE