TM 10--3510--221--10
0024 00--9
LAUNDRY ADVANCED SYSTEM
PREVENTIVE MAINTENANCE CHECKS AND SERVICES -- Continued
0024 00
TABLE 1. Operator PMCS -- Continued.
ITEM
NO.
INTERVAL
MAN--
HOUR
ITEM TO BE
CHECKED OR
SERVICED
PROCEDURE
EQUIPMENT
NOT READY/
AVAILABLE
IF:
15
Before
Detergent supply
Check for adequate supply of detergent in
external container (36).
Detergent
supply is < 1
gal
Ensure pickup tube (37) is inserted
completely into detergent container.
Pickup tube is
not fully
inserted
Ensure petcock (38) on main control
enclosure (39) is open.
Petcock is
closed
16
Before
Lint filters
Ensure lint filters (40) are cleaned and
installed and latches (41) are engaged.
Lint filter is not
clean, not
installed or
latches are not
engaged
17
Before
Washing/drying
drums
Ensure sluice lids (42) are closed and
latches (43) are engaged.
Lids are not
closed and
locked
Ensure retaining pins (44) are not installed.
Pins are
installed
Ensure load binders (45) are not installed.
Load binders
are installed
Ensure four air bag petcocks (46) are
closed.
Petcocks are
open
Ensure shutoff valve (47) is open.
Valve is closed
Check drum baskets (48) for free rotation
with no binding.
Baskets do not
rotate freely
Inspect windows (49) in center of doors
(50) for cracks and signs of leakage.
Window is
cracked or
leaking
Inspect gaskets (51) on back side of doors
(50) for tears.
Gaskets are
torn
18
Before
Subcooler
Ensure inlet screen (52) is not blocked with
debris.
Screen is
blocked
Ensure eight petcocks (53) are closed.
Petcocks are
open
19
Before
Evaporative
cooler
Ensure air filters (54) are not blocked with
debris.
Screens are
blocked
20
Before
Coalescer
Ensure petcock (55) is closed.
Petcock is open
21
Before
Distillate pump
Ensure petcock (56) is closed.
Petcock is open