1. Pull out on locking tab (6), then install new circuit breaker (1) onto mounting rail (7).
2. Loosen screw terminals (5), then connect wires as tagged.
3. Insert bus bar (3) into circuit breakers (1 and 4), then tighten screw terminals (2 and 5).
4. Position lever (8) to ON.
5. Turn handle (9) CW, then close door (10).
6. Secure door (10) to main control enclosure (11) by tightening eleven latches (12).
7. Using maintenance menu (WP 0010 00) verify correct operation as follows:
a. For circuit breaker CB1 test still condenser fan M200 and thermal fluid pump M300 operation. Also test
heating system.
b. For circuit breaker CB2 test dryer blower motors M104A and B operation.
c. For circuit breaker CB3 test drum motor M100A rotation.
d. For circuit breaker CB4 test drum motor M100B rotation.
e. For circuit breaker CB5 test water pumps M101A and M101B operation.
f. For circuit breaker CB6 test water pump M105, distillate pump (M201), and air compressor (M500) operation.
END OF WORK PACKAGE