TM 10-3510-224-13&P
0009 00
Table 1. Preventive Maintenance Checks and Services for the CSSL-Continued.
0009 00-8
Item
No.
Interval
Item to be
checked or
serviced
Procedure
Equipment not ready/available if:
36
Weekly
Exterior GFCI
Receptacle
Check for security of connections. Check
for damaged or missing hardware. Push
the TEST button. Observe the light
indicator. If the indicator does not
activate, push the RESET button. Repeat
the test. If the receptacle does not work,
notify Unit Maintenance.
GFCI outlet damaged or inoperative. Missing
hardware.
Monthly PMCS procedures would be the same procedures as for weekly PMCS procedures, with the addition of placing more