TM 10--3510--221--24
0228 00--3/4 blank
PERISTALTIC PUMP REPAIR -- Continued
0228 00
INSTALLATION
1. Install new rollers (15) onto pins (16).
NOTE
When assembling roller mechanism flat spots on top and bottom brackets must be oriented
the same, or mechanism will not slide onto shaft.
2. Place pins (16) between top bracket (13) and bottom bracket (14).
3. Slide spring (10) onto top bracket (13) and bottom bracket (14).
4. Spread tabs on spring (10) then slide roller mechanism (11) onto shaft (12).
5. Cut a new piece of tube (4) to the same length as old tube.
6. Slide clamps (5 and 7) onto tube (4).
7. Connect tube (4) to elbow (8), then secure with clamp (7).
8. Connect tube (4) to tee (6), then secure with clamp (5).
9. Insert tube (4) between two rollers (15) and guide (17).
10. Install cover (2) onto peristaltic pump (3) then secure with four screws (1).
11. Using maintenance menu control outputs function (WP 0010 00) verify correct operation as follows:
a. Turn on detergent pump A, detergent pump B, or anti--foam pump and verfiy pump is operating.
b. Continue pump operation. When detergent or anti--foam fills tube (8) verify no leaks exist at tube
connections.
c. Turn off pump.
12. Turn handle (18) CW, then close door (19).
13. Secure door (19) to main control enclosure (9) by tightening eleven latches (20).
END OF WORK PACKAGE