TM 10--3510--221--24
0206 00--1
AIR BAG PRESSURE REGULATOR
REPLACEMENT
0206 00
THIS WORK PACKAGE COVERS:
Removal, Installation, Adjustment
INITIAL SETUP:
Maintenance Level
Materials/Parts
Unit
Tape, Anti--Seizing (Item 10, WP 0271 00)
Tools and Special Tools
Equipment Conditions
Tool Kit, General Mechanics (Item 1, WP 0272 00)
LADS power shut off at main control
enclosure (WP 0112 00).
REMOVAL
1. Disengage two latches (1), then open access door (2).
2. Close manual valve (3).
3. Open petcock (4), allow product air to vent, then close petcock.
4. Disconnect tube (5) from connector (6).
5. Disconnect tube (7) from connector (8).
6. Loosen panel nut (9) then remove pressure regulator (10) from bracket (11).
7. Unthread connectors (6 and 8) from pressure regulator (10).
8. Clean anti--seizing tape from threads of connectors (6 and 8).
2
1
3
4
ROTATED 90_
5
13
12
614
8
7
11
10
9