TM 10-1670-300-20&P
TO 14D1-2-469-2
NAVAIR 13-1-42
SERVICE
NOTE
FF-2 releases attaining 25 live operations since being placed m service from depot
storage or previous cleaning of 365 days of service will be considered unserviceable
even if they pass all functional tests Unserviceable FF-2 releases will be serviced in
accordance with these procedures.
FF-2 releases attaining 200 live operations or four years of service from depot storage
will be evacuated to Depot for overhaul by manufacturer.
a.
Initiate DA Form 2404 or locally approved form (see Figure 2-<REF> for example).
Figure 2-1. SAMPLE LOCALLY APPROVED FORM
2-37